ISO New England has launched its first transitional cluster study examining 26 interconnection requests representing approximately 8 gigawatts of clean energy capacity. The review includes 21 battery storage projects alongside wind and solar developments, with completion expected by August 2026.
Major Grid Interconnection Study Launched
ISO New England has initiated what sources describe as a significant transitional cluster study involving 26 interconnection requests with a combined summer capacity of approximately 8 gigawatts, according to reports from the grid operator. The comprehensive review, announced this week, represents a new approach to managing the region’s growing queue of renewable energy and storage projects seeking connection to the electrical grid.